Problem statement
A typical problem for running shoes is spike damage when walking on hard surfaces causing decreased spike performance. The purpose of this design is to prevent spike damages with a durable design that can utilize multiple components. Each component must be expressed through professional engineering drawings that detail important tolerance, dimension, and material information.
Assumptions
Assumed that each component drawing accounts for part interferance.
Decision Matrix
Decision Matrix Link
Solutions
Most Significant Componet: Rail/Track
Component 1: Rail/Track
Track
Component 2: Shoe Sole
Shoe-Sole
Component 3: Twist Screw Clamp
Track
Assembly View
Track
Gantt Chart
Gantt Chart Link
Lessons Learned
1)Reviewed engineering drawings
2)Reviewed engineering tolerances on parts that interfere
3)Learned how to scale drawings
Advisee comments
Advisee 1 (Cody Davis): Everything looks good. The drawing files were not in pdf form at the time of checking. Advisee comments not up yet.
Picked Advisee (Grayson Roberts): Everything looks good. I would recommend increasing the size of your gantt chart.